The contract for the construction of the WAPP Information and Coordination Center (ICC) located in Calavi was signed in August 2016. The completion of the building is planned in 2018. The contract for equipment and software is being signed by the contractor sélected. The completion of the equipment installation is expected in 2019
WAPP to continue to coordinate and monitor the implementation of the project
In service year | 2018 |
Project Cost | 41 |
Funds Secured | 41 |
Funding Sources | EU |